NMDOT assessing erosion damage at Belen river bridge

Erosion on the north side of the Belen river bridge has led to exposed utility lines and a complete closure of the bridge, meaning there's no direct access to the Hub City from the east side of the Rio Grande.
Submitted photo

BELEN — An excess of water has once again caused the closure of a critical bridge in Valencia County.

Shortly after 6 p.m., Thursday, Nov. 5, the New Mexico Department of Transportation issued an alert advising motorists that N.M. 309 in Belen, more commonly known as East River Road, was closed at the bridge across the Rio Grande “due to concerns involving conditions near the roadway and bridge.”

Photos provided to the News-Bulletin showed erosion damage on the north side of the bridge, a rusted, collapsed culvert and exposed utility lines.

In an interview Friday morning, Valencia County Fire Chief Matt Propp said his understanding of the situation is a large area of erosion has been identified under the bridge due to water flow outside the river’s normal flow.

“You can see where it is going in under the bridge, but not where it’s coming out,” Propp said. “It seems like the concern is it will create a sinkhole under (the east end) of the bridge.”

If the scenario at the Belen river bridge sounds familiar, that’s because it is strikingly similar to an erosion issue in the village of Los Lunas in the spring of 2023. High water levels in a Middle Rio Grande Conservancy District riverside drain near the Los Lunas river bridge on Main Street (N.M. 6) caused erosion under the east side of that structure, resulting in an immediate closure, followed by nearly six months of repairs.

Erosion on the north side of the Belen river bridge shows a collapsed culvert which may have led to water moving under the bridge and roadway. Due to unknown conditions of the structure, the state department of transportation has implemented a complete closure of the bridge, meaning there's no direct access to the Hub City from the east side of the Rio Grande.
Submitted photo

Jason Casuga, the chief engineer and CEO of the MRGCD, said the Belen incident is very similar to the 2023 event.

“(NMDOT) has a facility that goes over ours,” Casuga said.

In the case of the Belen closure, N.M. 309/E. River Road crosses the district’s San Juan Feeder before it intersects with N.M. 47.

“There is a pipe underground that exists for us to go under (the road) that’s eroded. Like the Los Lunas situation, the infrastructure — the road, bridge and the pipe — is NMDOT’s,” Casuga said.

In the 2023 Los Lunas situation, the riverside drain was part of MRGCD infrastructure, but the culverts under the highway were supposed to be maintained by NMDOT.

Regardless who was supposed to maintain what, the bridge closure has thrown a logistical monkey wrench into the regular commute for hundreds of Valencia County residents and necessitated quick adjustments to bus routes for Belen Consolidated Schools.

Belen Superintendent Lawrence Sanchez said buses used N.M. 346 in Bosque to cross the river to pick up students Friday morning.

“There were some delays Friday morning, about 10 to 15 minutes is what I understand. Now our drivers are finalizing a plan for morning route changes, which will be sent out later this afternoon,” Sanchez said. “We don’t know what the drop off schedule will be because we haven’t run the afternoon routes yet. Once we know what those updated routes will look like, we will let parents know.”

The superintendent said the districts transportation staff and drivers were outstanding Thursday evening, making a quick pivot and calling each parent personally to let them know what the new morning pick up time would be for their students on Friday.

“Once we know what the afternoon schedule will be, we’ll let parents know,” he said.

Adjusted pick up and drop off information will be posted to the district’s Facebook page — Belen Consolidated Schools. Parents will receive a text message directing them to the social media platform once that information is available, the superintendent said.

“It will be the same way it was sent out (Thursday) night. We are limited to 138 characters on SMS, so the message will direct them to go to our Facebook page,” Sanchez said, urging parents to look for information on the district’s Facebook page, website or what’s been shared with the News-Bulletin.

“People were calling me, saying they’d seen information posted that buses were canceled for Friday. That’s not what we posted, so please look for official information,” the superintendent said.

Kimberly Gallegos, spokeswoman for NMDOT District 3, said department engineers would be on site Friday afternoon to assess the situation at the river bridge.

“They are going to try to get a camera down there to see where the issue is and how severe it is,” Gallegos said.

Once a full assessment has been done, NMDOT will determine what, if any, traffic will be allowed on the bridge. It’s closed to vehicle traffic and pedestrian traffic as of now, she said, “until our engineers determine the severity.”

She said the department is working with MRGCD to figure out how to best handle the situation.

In the meantime, Gallegos encouraged people to use alternate routes to get across the river, which includes N.M. 6/Main Street in Los Lunas and N.M. 346 in Bosque and N.M. 60 in Bernardo, which are both south of the Belen river bridge. N.M. 47 remains fully open at this time.

Regular updates on the closure can be found on nmroads.com.

A statement issued on Facebook on Friday, Nov. 6 by Rio Communities Mayor Joshua Ramsell said NMDOT began assessing the possible sinkhole and structural integrity of the bridge that day.

“Emergency service officials from the city and county have met and coordinated preparations for this closure,” Ramsell’s statement reads. “In the meantime, we ask residents to remain patient as this closure causes and changes to daily commutes...Please allow additional travel time, follow posted detours and do not enter the closed area or drive around barricades.”