Voters to answer general obligation bond questions

GENERAL ELECTION 2026

Valencia County asking for $9 million in GO bonds for capital projects, equipment

Stock image

Four questions on the November ballot could result in a total of $9 million for capital projects across Valencia County if they are approved by voters.

In August, Valencia County commissioners approved four separate general obligation bond questions to be put out to the voters — $1 million for public safety for the sheriff’s office and fire department facilities, $4 million for road improvements, $2 million for community centers and county facilities and $2 million for parks and recreation.

If the new GO bonds are passed this year, the rate of .87 mils will remain the same for property taxpayers.

“These bonds will improve the quality of life in Valencia County,” said Valencia County Manager Jhonathan Aragon. “As long as I’ve been a part of the county (as a commissioner and the manager) they have been approved and used in a positive way. It’s nice that this will not increase the tax rate because it is a continuation. So many projects are able to get started and sometimes finished with this funding.”

Aragon said funding from GO bonds goes hand-in-hand with capital outlay money the county receives from the state Legislature.

“We look at projects that make it onto our (Infrastructure Capital Improvement Plan) that goes to the legislators,” he said. “The amounts we get from the bonds allows us to continue large projects. We know for the most part what to expect from the legislature, but it by no means covers everything.”

$1 million for public safety

Aragon said there are three primary projects identified to address public safety in the county.

The first is a new fire station on N.M. 6 west of the village of Los Lunas in the unincorporated area of San Clemente. The manager said when looking at ISO fire ratings, which directly impact insurance rates for residential and commercial properties, long distances between fire services increases those rates.

Currently, the closest fire stations to the area are the county’s station in Highland Meadows and the village’s station on Sand Sage Road, leaving a large area between the two with limited coverage. Aragon said the county has been working with the developers of the Central New Mexico Rail Park on N.M. 6 to obtain property for a new station.

A second project is a multi-use training facility for all of the county’s first responders, rather than a facility for each department, “which will give us better trained officers, firefighters and paramedics, so in high stress situations, there will be better responses from everybody.”

A third priority for the funding is for the replacement of firefighter apparatus, ranging from vehicles to AEDs.

“Everything has to be replaced at some point, maybe it’s a one-time use or after a year or two,” Aragon said. “Other equipment has a long life, but needs regular inspections.

“We have legislators (who) invest in our public safety and maybe we can knock off some of the higher-value projects with (legislative) appropriations, but things that are lower on the ICIP can be covered by the bonds.”

$4 million for roads

While $4 million is a healthy chunk of change, it doesn’t stretch very far for roads, the manager said. The rule of thumb used to be $1 million would pay for about 10 miles of road, “now it’s a mile, maybe even less.”

Roads in school zones and on school bus routes, those that lead to public facilities, major thoroughfares and high-volume roads are where the county will focus the larger amounts of money, Aragon said.

“Road projects are high cost and we need to be strategic. Our roadways are critical places and they need to be safe,” he said.

He acknowledged residents want to know which specific roads will be targeted for bond funding and would like to see them named in the ballot question, but that’s not always the best approach.

“It’s hard to put in specific roads. Let’s say we have four miles of road and repair costs are estimated at $4 million, but it’s ends up being $5 million. Now we’re in a position where we have to take away from our capital infrastructure (pot of money) and fund that road instead of maybe doing five smaller projects,” he said. “By having the questions be broad, we have the ability to be flexible. The money has to be used for the purpose approved but maybe a different project within that purpose based on actual costs.

“We have to stretch these dollars as best we can, in the most strategic way so the community has something to show for the investment they voted on. We want to see projects started and completed.”

Other purchases the bond funds could be used for is heavy equipment such as graders, rollers and trucks for the county public works department so employees can do minor repairs and road work in house.

$2 million for community centers, county facilities

The “newbie” project in the county is the Valencia County Fairgrounds, Aragon said, noting there are a lot of plans for the property in Belen.

“It’s a new project we hope to grow a lot more in the future. It’s currently under architectural review and design. We have a lot of help from the Legislature on that project,” he said.

There is already some funding for a senior center in Highland Meadows on the far western edge of the county, but the hope is some of the bond will be used to continue the project.

A community center on the east side of the county — El Cerro Mission — is on the list for improvements. Aragon said it’s one of the more underutilized buildings in the county’s inventory and work there would be part of the county’s overall goal to improve services to its centers and grow the parks and recreation department.

“We are adding amenities as funding comes available,” the manager said.

$2 million for parks and recreation

From equipment to facilities, open space, bike and walking paths, Aragon said the county is hoping to stretch the $2 million across numerous projects, including a possible splash pad at the park in Las Maravillas the county recently acquired and renovated.

Improvements will continue to be made at Meadow Lake Park, the county’s most-used facility, he said, as well as Willie Chavez Park in Belen, which is what he described as a “more natural park” with connection to the bosque.

Previous bond projects

In 2022, the four bond questions on the ballot were $1 million for sheriff and fire department facilities, $4 million for county roads, $1.5 million for parks and recreation facilities and $1.5 million for community and senior centers, for a total of $8 million. All four measures were approved by the voters.

Projects paid for from those bonds include bunkrooms at the Highland Meadows Fire Station, renovations at fire stations 9 and 10, improvements to the Valencia County Sheriff’s Office evidence room, heavy equipment for the public works department, signs and lighting on El Cerro Mission Boulevard, Highland Meadows park construction, design for improvements at the Del Rio Senior Center, as well and kitchen equipment and fire alarms for the center and equipment and improvements at the Meadow Lake Community Center.