Efficient Engineering Shaves 47% off the Design Cost of our Client's Structure

Getting The Correct Dimensions
The client had originally approached an independent engineer who had unfortunately failed to measure the structure correctly.
“The dimensions of the structure were quite far off and the bays were oversized for the client’s needs,” explains Shane.
“I visited the site in person to measure up correctly, and we were able to reduce the dimensions of the structure from 30m to 21.5m long. The bays were also originally set at 10m wide, however, they only needed to be 7.16m wide to suit the client’s application.”
Saving over 2.8m on each bay and 8.5 metres of building length brought the design cost down immediately.
Using Efficient Engineering
Reducing the size of the building was one factor, but drastically reducing the amount of steel in the structure played a significant role in achieving savings for our client.
Shane notes that whilst many forward-thinking engineers maintain a strong focus on efficiency, it’s an unfortunate fact that many in the industry do not, instead selecting outsized components and unnecessarily heavy steel.
“The original engineer was using 380PFC steel which is 55kg per metre. Our engineering team revised the design, reducing the steel to 150 x 100 x 5 RHS which comes in at just 18kg per metre,” says Shane.
“Not only does this save on the quantity of steel required, but we’ve also reduced the weight of the steel dramatically. This has the knock-on effect of reducing the carbon footprint of the building too, as less material is required to achieve a strong, robust and perfectly serviceable result that is more efficient – and costs much less."

"The original design cost was sitting at $270,000 however our new efficient design cost came out at just $143,000. That’s $127K back in our client’s pocket simply by taking a smart, sustainable approach to designing their structure.”
- Shane Barker

The Result – Massive Savings.
Overall, the design changes implemented by our engineering team resulted in a cost reduction of $127,000.
“The original design cost was sitting at $270,000 however our new efficient design cost came out at just $143,000,” says Shane.
“That’s $127K back in our client’s pocket simply by taking a smart, sustainable approach to designing their structure.”
Avoid Cost Blowouts with Steelcorp
Don’t let an inefficient, over-engineered design drive up the cost of your building project. Contact our team to get an efficient design that prioritises cost-effectiveness and strength without excess material use.