‘They’re on notice’: Upper Mount Bethel board gives supervisors 60 days to take action on data center regulation

Slate Belt Holdings, a partnership between Talen Energy and River Pointe Logistics, included this map as part of its preliminary land development plans sent to Upper Mount Bethel Township on Tuesday, Oct. 13, 2026. This proposed hyperscale campus layout includes 29 data center buildings and reflects previous plans sent to the township as part of two validity challenges filed against its zoning ordinance. (Slate Belt Holdings)
Slate Belt Holdings, a partnership between Talen Energy and River Pointe Logistics, included this map as part of its preliminary land development plan submitted to Upper Mount Bethel Township on Tuesday, Oct. 13, 2026. This is an alternate layout design for the proposed hyperscale data center campus that includes fewer, smaller buildings. (Slate Belt Holdings)

Facing three tables of lawyers Monday night, the Upper Mount Bethel Township Zoning Hearing Board decided it’s not yet time to make a ruling on a hyperscale data center developers’ challenge to the township’s zoning ordinance.

The board postponed its consideration of developer Slate Belt Holdings’ validity challenge until Dec. 17, voting to give township supervisors 60 days to take action on data center regulation.

What action the board expects from the supervisors remains unclear. Ron Angle, the zoning board alternate member who made the motion to pass the issue to supervisors, did not directly answer that question when asked for clarification.

“I anticipate that the supervisors would do the job that the citizens of this township elected them to do,” Angle said, adding that “they’re going to be on notice.”

Next steps were not immediately apparent to supervisors Chair John Bermingham, who told The Morning Call, “I don’t know what I’m supposed to do in 60 days.”

Zoning hearing board solicitor Chad DiFelice told The Morning Call that his understanding of the board’s intent is to give supervisors 60 days to either advance a data center ordinance that has not yet been adopted or take action on memorandums of understanding with the project developer that have been discussed at length at supervisors’ meetings.

Slate Belt Holdings, a partnership between Talen Energy and River Pointe Logistics, proposed a memorandum of understanding in August that would have ended the legal challenge to township zoning laws and promised up to $50 million in donations, if officials collaborated on zoning changes regarding data centers and eventually approved Slate Belt’s plans.

Multiple versions of that deal have been considered as both developers and supervisors proposed adjustments to the original terms. Discussions stalled as supervisors split in strategy between those who argue that direct negotiation with developers is the best route to winning environmental protections and those who say the focus should be on passing the township’s long-delayed data center ordinance.

Under pressure, Lehigh Valley township reconsiders developers’ role in data center regulation

Long-delayed regulation

DiFelice and members of the zoning board emphasized that it’s been two and half years since the township zoning officer was asked to interpret how Upper Mount Bethel’s ordinances would apply to data center development, but supervisors have not yet passed a data center ordinance.

Supervisors sent their latest draft data center ordinance to the Lehigh Valley Planning Commission for review Sept. 21. A March 2025 version, drafted after Amazon showed interest in a data center deal, was never finalized.

Discussions with Amazon, which began in 2024, did not advance to a formal data center proposal. Upper Mount Bethel has now received land development plans from Slate Belt, which submitted two potential site designs and an updated proposal for a $50 million community benefits agreement Oct. 13.

Slate Belt included the April 2024 zoning determination in its validity challenge filing. In opening discussions Monday, attorney Shawn Gallagher said the zoning hearing officer had “nailed it,” arguing that the determination clearly states a data center is permitted by right.

Township solicitor Bill Jones, newly hired to join Upper Mount Bethel’s defense of its zoning ordinance, said plans submitted in April 2024 didn’t include proposed square footage and the township’s ordinances state that total square footage determines whether a developer would need a special exception.

Those legal arguments were part of preliminary public discussions about what was at stake Monday night and which parties had standing to join the hearing. The zoning hearing board voted 4-1 to postpone the hearing before formally considering evidence or testimony.

Next steps

The Delaware Riverkeeper Network was granted standing to join the case Monday. The environmental advocates presented a list of 27 members who live within half a mile of the proposed data center campus who authorized the organization to represent their interests. Another township resident who lives in that radius but is not a network member was also granted standing.

The two-month extension of the hearing will allow for “an appropriate opportunity for the community to review the facts and develop their case,” Riverkeeper Maya van Rossum told The Morning Call.

Last week’s filing of land development plans gives the community much more information to review, van Rossum said.

Adding to the list of open questions is the fact that Upper Mount Bethel is facing a second zoning challenge related to an extension of the data center campus proposal. That challenge is set to be heard by November. It was not under legal consideration or public discussion Monday.

While the case scheduled to be heard Monday concerns plans to build 23 data center buildings and two substations on 754 acres of industrially zoned land west of River Road, the Oct. 8 challenge relates to a plan to add six data center buildings, battery storage and a power plant on approximately 152 acres east of River Road.

The latest design plans offer two versions of how data center buildings would be placed on those 900 acres, with one option featuring 29 data center buildings that total 3.5 million square feet and a second option featuring six data center buildings totaling nearly 1.5 million square feet.

A spokesperson for the development team told The Morning Call that partners envision the project as having multiple phases and added that the second legal challenge is an attempt to clarify how zoning regulations would apply to the total proposed buildout.